You have the schedule the following jobs:
Job | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Processing time | 3 | 6 | 8 | 4 | 2 | 7 | 1 |
Deadline | 4 | 8 | 9 | 12 | 13 | 16 | 30 |
Schedule to:
- Minimize the number of late orders
- Minimize the maximum tardiness
- Minimize the summation of completion times
Describe the approach you used and the meaning of its outcomes.